[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-781-16":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":726},{"id":5,"name":6,"category":7,"favorite":8},781,"目标控制（交通工程）","建筑工程",0,16,50,818,[13,38,53,67,82,96,110,124,139,153,167,182,196,210,224,238,251,265,279,293,306,320,334,348,362,376,390,404,418,428,442,456,471,486,500,515,529,543,557,571,585,599,613,628,642,656,670,684,698,712],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},1106325,2,"多选题","以下关于考核评价结果说法错误的是（ ）",[19,23,27,30,33],{"key":20,"text":21,"correct":22},"A","平安工地建设考核评价按照百分制计算得分",false,{"key":24,"text":25,"correct":26},"B","计算得分精确到小数点后2位",true,{"key":28,"text":29,"correct":22},"C","考核评价结果分为合格、不合格两类",{"key":31,"text":32,"correct":26},"D","考核评价分数60分及以上的为合格",{"key":34,"text":35,"correct":22},"E","施工单位考核评价结果即为施工合同段考核评价结果,监理单位考核评价结果即为监理合同段考核评价结果","BD","",{"id":39,"libraryId":5,"type":15,"typeLabel":16,"stem":40,"options":41,"answer":52,"analysis":37},1106326,"（ ）的项目综合应急预案，按规定向属地直接监管的负有安全生产监督管理职责的交通运输管理部门和安全生产监督管理部门备案。",[42,44,46,48,50],{"key":20,"text":43,"correct":26},"国家高速公路",{"key":24,"text":45,"correct":26},"独立特大桥及特长隧道",{"key":28,"text":47,"correct":26},"10万吨级以上码头",{"key":31,"text":49,"correct":26},"航电枢纽等工程",{"key":34,"text":51,"correct":22},"复杂的边坡","ABCD",{"id":54,"libraryId":5,"type":15,"typeLabel":16,"stem":55,"options":56,"answer":52,"analysis":37},1106327,"安全生产隐患，是指生产经营单位违反安全生产相关制度等规定，或因其他因素在生产经营活动中存在的（ ）。",[57,59,61,63,65],{"key":20,"text":58,"correct":26},"人的不安全行为",{"key":24,"text":60,"correct":26},"物的不安全状态",{"key":28,"text":62,"correct":26},"场所的不安全因素",{"key":31,"text":64,"correct":26},"管理上的缺陷",{"key":34,"text":66,"correct":22},"工作上的失误",{"id":68,"libraryId":5,"type":15,"typeLabel":16,"stem":69,"options":70,"answer":81,"analysis":37},1106328,"平安工地建设管理主要包括（ ）。",[71,73,75,77,79],{"key":20,"text":72,"correct":26},"工程开工前的安全生产条件审核",{"key":24,"text":74,"correct":26},"施工前的安全生产条件核查",{"key":28,"text":76,"correct":26},"施工过程中的平安工地建设、考核评价",{"key":31,"text":78,"correct":22},"交工期间的安全考核",{"key":34,"text":80,"correct":22},"缺陷责任期的安全考核","ABC",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":81,"analysis":37},1106329,"公路水运工程项目生产安全事故应急预案（以下简称项目预案）。项目预案是公路水运工程项目建设或施工等参建单位制定的生产安全事故应急预案。项目预案包括（ ）。",[86,88,90,92,94],{"key":20,"text":87,"correct":26},"项目综合应急预案",{"key":24,"text":89,"correct":26},"合同段施工专项应急预案",{"key":28,"text":91,"correct":26},"现场处置方案",{"key":31,"text":93,"correct":22},"现场处理方案",{"key":34,"text":95,"correct":22},"综合演练预案",{"id":97,"libraryId":5,"type":15,"typeLabel":16,"stem":98,"options":99,"answer":109,"analysis":37},1106330,"双重预防机制是指以（ ）和（ ）两种手段相结合的生产安全事故预防机制。",[100,102,104,106,108],{"key":20,"text":101,"correct":26},"风险分级管控",{"key":24,"text":103,"correct":26},"隐患排查治理",{"key":28,"text":105,"correct":22},"现场应急预案",{"key":31,"text":107,"correct":22},"综合应急预案",{"key":34,"text":91,"correct":22},"AB",{"id":111,"libraryId":5,"type":15,"typeLabel":16,"stem":112,"options":113,"answer":52,"analysis":37},1106331,"隐患治理工作应坚持（ ）的原则。",[114,116,118,120,122],{"key":20,"text":115,"correct":26},"单位负责",{"key":24,"text":117,"correct":26},"行业监管",{"key":28,"text":119,"correct":26},"分级管理",{"key":31,"text":121,"correct":26},"社会监督",{"key":34,"text":123,"correct":22},"内部执行",{"id":125,"libraryId":5,"type":15,"typeLabel":16,"stem":126,"options":127,"answer":138,"analysis":37},1106332,"平安工地建设监理方案可作为安全监理计划的主要内容，也可单独编制，作为安全监理计划的补充文件，其主要内容有（ ）。",[128,130,132,134,136],{"key":20,"text":129,"correct":26},"编制依据",{"key":24,"text":131,"correct":22},"资金情况",{"key":28,"text":133,"correct":26},"平安工地建设目标",{"key":31,"text":135,"correct":26},"组织机构",{"key":34,"text":137,"correct":26},"监理机构平安工地建设","ACDE",{"id":140,"libraryId":5,"type":15,"typeLabel":16,"stem":141,"options":142,"answer":138,"analysis":37},1106333,"下列情形属于Ⅱ级事故的有（ ）。",[143,145,147,149,151],{"key":20,"text":144,"correct":26},"10人以上死亡（含失踪）",{"key":24,"text":146,"correct":22},"直接经济损失1000万元以下",{"key":28,"text":148,"correct":26},"50人以上重伤",{"key":31,"text":150,"correct":26},"直接经济损失5000万元以上",{"key":34,"text":152,"correct":26},"省政府责成省级交通运输主管部门组织处置的事故",{"id":154,"libraryId":5,"type":15,"typeLabel":16,"stem":155,"options":156,"answer":52,"analysis":37},1106334,"下列选项中，应开展施工安全风险评估的桥梁工程有（ ）。",[157,159,161,163,165],{"key":20,"text":158,"correct":26},"多跨或跨径大于40m的石拱桥",{"key":24,"text":160,"correct":26},"跨径大于或等于140m的梁式桥",{"key":28,"text":162,"correct":26},"特殊桥型或特殊结构桥梁的拆除或加固工程",{"key":31,"text":164,"correct":26},"跨径大于1000m的悬索桥",{"key":34,"text":166,"correct":22},"跨径大于140m的斜拉桥",{"id":168,"libraryId":5,"type":15,"typeLabel":16,"stem":169,"options":170,"answer":181,"analysis":37},1106335,"下列选项中，属于在充分分析工程风险因素、事故起因、救援经过的基础上，重点评估以下内容的有（ ）。",[171,173,175,177,179],{"key":20,"text":172,"correct":22},"邀请专家协助开展评估",{"key":24,"text":174,"correct":26},"预防预警和预控措施",{"key":28,"text":176,"correct":26},"信息报送的时效性与准确性",{"key":31,"text":178,"correct":26},"事故救援组织机构设置及运行",{"key":34,"text":180,"correct":26},"技术方案及实施情况","BCDE",{"id":183,"libraryId":5,"type":15,"typeLabel":16,"stem":184,"options":185,"answer":138,"analysis":37},1106336,"下列选项属于施工安全风险评估报告的编制依据的有（ ）。",[186,188,190,192,194],{"key":20,"text":187,"correct":26},"项目风险管理方针及策略",{"key":24,"text":189,"correct":22},"建立施工安全风险评估制度",{"key":28,"text":191,"correct":26},"项目设计和施工方面的文件",{"key":31,"text":193,"correct":26},"项目各阶段的审查意见",{"key":34,"text":195,"correct":26},"设计阶段风险评估意见",{"id":197,"libraryId":5,"type":15,"typeLabel":16,"stem":198,"options":199,"answer":52,"analysis":37},1106337,"重大风险信息报备主要内容包括（ ）。",[200,202,204,206,208],{"key":20,"text":201,"correct":26},"基本信息",{"key":24,"text":203,"correct":26},"管控信息",{"key":28,"text":205,"correct":26},"预警信息",{"key":31,"text":207,"correct":26},"事故信息",{"key":34,"text":209,"correct":22},"生产信息",{"id":211,"libraryId":5,"type":15,"typeLabel":16,"stem":212,"options":213,"answer":81,"analysis":37},1106338,"施工单位的三级安全教育即（ ）。",[214,216,218,220,222],{"key":20,"text":215,"correct":26},"公司级培训教育",{"key":24,"text":217,"correct":26},"项目部级培训教育",{"key":28,"text":219,"correct":26},"班组级安全教育",{"key":31,"text":221,"correct":22},"应急安全教育",{"key":34,"text":223,"correct":22},"安全继续教育",{"id":225,"libraryId":5,"type":15,"typeLabel":16,"stem":226,"options":227,"answer":52,"analysis":37},1106339,"招标阶段安全监理主要工作（ ）。",[228,230,232,234,236],{"key":20,"text":229,"correct":26},"审查投标单位的安全生产许可证（副本原件）是否为有效证件",{"key":24,"text":231,"correct":26},"审查投标单位的资质证书（副本原件）、营业执照（副本原件）、诚信记录、资信等级是否符合招标文件要求",{"key":28,"text":233,"correct":26},"审查三类人员（企业主要负责人、项目经理、专职安全管理员）安全资格证书",{"key":31,"text":235,"correct":26},"协助建设单位拟定工程施工安全生产协议书",{"key":34,"text":237,"correct":22},"督促施工单位监理安全领导小组",{"id":239,"libraryId":5,"type":15,"typeLabel":16,"stem":240,"options":241,"answer":52,"analysis":37},1106340,"施工单位的安全培训教育的分类包括（ ）。",[242,244,246,248,250],{"key":20,"text":243,"correct":26},"“三类人员”培训教育",{"key":24,"text":245,"correct":26},"特种作业人员培训教育",{"key":28,"text":247,"correct":26},"进场安全教育",{"key":31,"text":249,"correct":26},"三级安全教育",{"key":34,"text":223,"correct":22},{"id":252,"libraryId":5,"type":15,"typeLabel":16,"stem":253,"options":254,"answer":181,"analysis":37},1106341,"下列哪些选项属于建设单位的安全生产责任？（ ）",[255,257,259,261,263],{"key":20,"text":256,"correct":22},"按规定主动接受建设单位的安全检查、审核",{"key":24,"text":258,"correct":26},"保证安全生产专项资金的投入",{"key":28,"text":260,"correct":26},"核查施工单位和指定分包单位的安全资质",{"key":31,"text":262,"correct":26},"督促施工单位对施工人员进行安全教育",{"key":34,"text":264,"correct":26},"向施工单位提供与施工现场相关的地下管线资料",{"id":266,"libraryId":5,"type":15,"typeLabel":16,"stem":267,"options":268,"answer":52,"analysis":37},1106342,"下列哪些选项属于投标文件符合性的审查？（ ）",[269,271,273,275,277],{"key":20,"text":270,"correct":26},"安全生产管理机构",{"key":24,"text":272,"correct":26},"安全生产管理网络",{"key":28,"text":274,"correct":26},"安全生产规章制度和操作规程",{"key":31,"text":276,"correct":26},"安全生产方面奖惩情况",{"key":34,"text":278,"correct":22},"安全生产许可证审查",{"id":280,"libraryId":5,"type":15,"typeLabel":16,"stem":281,"options":282,"answer":138,"analysis":37},1106343,"下列选项属于安全监理计划编制内容的有（ ）。",[283,285,287,289,291],{"key":20,"text":284,"correct":26},"工程概况",{"key":24,"text":286,"correct":22},"安全监理人员安排及分工",{"key":28,"text":288,"correct":26},"监理依据",{"key":31,"text":290,"correct":26},"安全监理工作制度建设",{"key":34,"text":292,"correct":26},"安全监理工作计划",{"id":294,"libraryId":5,"type":15,"typeLabel":16,"stem":295,"options":296,"answer":305,"analysis":37},1106344,"下列选项属于安全监理实施细则编制内容的有（ ）。",[297,298,300,302,303],{"key":20,"text":286,"correct":26},{"key":24,"text":299,"correct":26},"现场安全监理检查的控制要点",{"key":28,"text":301,"correct":26},"安全监理工作方法和措施",{"key":31,"text":290,"correct":22},{"key":34,"text":304,"correct":26},"监理程序及表格和资料目录","ABCE",{"id":307,"libraryId":5,"type":15,"typeLabel":16,"stem":308,"options":309,"answer":138,"analysis":37},1106345,"下列选项属于核查施工单位特种人员持证上岗情况的核查要点有（ ）。",[310,312,314,316,318],{"key":20,"text":311,"correct":26},"特种作业人员种类",{"key":24,"text":313,"correct":22},"设备操作规程制订情况",{"key":28,"text":315,"correct":26},"核查特种作业人员证件合规性",{"key":31,"text":317,"correct":26},"核查安全培训教育及考核情况",{"key":34,"text":319,"correct":26},"检查施工单位特种作业人员台账更新情况",{"id":321,"libraryId":5,"type":15,"typeLabel":16,"stem":322,"options":323,"answer":181,"analysis":37},1106346,"下列选项属于施工安全技术措施的有（ ）。",[324,326,328,330,332],{"key":20,"text":325,"correct":22},"安全生产组织体系",{"key":24,"text":327,"correct":26},"进入施工现场的安全规定",{"key":28,"text":329,"correct":26},"水上、高处及立体交叉施工作业的防护",{"key":31,"text":331,"correct":26},"施工用电安全技术措施",{"key":34,"text":333,"correct":26},"预防自然灾害",{"id":335,"libraryId":5,"type":15,"typeLabel":16,"stem":336,"options":337,"answer":81,"analysis":37},1106347,"从业人员按照防护用品的使用规则和防护要求，正确使用防护用品。职工做到“三会”,即（ ）",[338,340,342,344,346],{"key":20,"text":339,"correct":26},"会检查防护用品的可靠性",{"key":24,"text":341,"correct":26},"会正确使用防护用品",{"key":28,"text":343,"correct":26},"会正确维护保养防护用品",{"key":31,"text":345,"correct":22},"会扑救初起火灾",{"key":34,"text":347,"correct":22},"会引导安全疏散",{"id":349,"libraryId":5,"type":15,"typeLabel":16,"stem":350,"options":351,"answer":81,"analysis":37},1106348,"交工验收阶段监理工程师主要工作内容包括（ ）。",[352,354,356,358,360],{"key":20,"text":353,"correct":26},"协助建设单位落实工程建设项目“三同时”的规定",{"key":24,"text":355,"correct":26},"审查安全设施等是否按设计要求与主体工程同时建成交付使用",{"key":28,"text":357,"correct":26},"承担交工验收至竣工验收阶段质量缺陷和问题修复施工作业安全管理责任",{"key":31,"text":359,"correct":22},"检查施工单位的施工台账",{"key":34,"text":361,"correct":22},"检查施工单位的三类人员的证件",{"id":363,"libraryId":5,"type":15,"typeLabel":16,"stem":364,"options":365,"answer":52,"analysis":37},1106349,"施工阶段监理工程师日常安全监理实施程序（ ）。",[366,368,370,372,374],{"key":20,"text":367,"correct":26},"发出口头通知，开具整改通知单",{"key":24,"text":369,"correct":26},"召开专题监理例会",{"key":28,"text":371,"correct":26},"签发工程停工令",{"key":31,"text":373,"correct":26},"向建设主管部门报告",{"key":34,"text":375,"correct":22},"编制好安全监理细则",{"id":377,"libraryId":5,"type":15,"typeLabel":16,"stem":378,"options":379,"answer":305,"analysis":37},1106351,"安全生产专项费用计量支付的工作内容包括（ ）。",[380,382,384,386,388],{"key":20,"text":381,"correct":26},"审查施工单位月度安全生产费用清单合规性",{"key":24,"text":383,"correct":26},"监理审核当月实际使用安全经费台账",{"key":28,"text":385,"correct":26},"现场核查施工单位安全生产费用实际使用情况",{"key":31,"text":387,"correct":22},"总监办签认后，报建设单位审批",{"key":34,"text":389,"correct":26},"建立安全生产费用监理审核台账",{"id":391,"libraryId":5,"type":15,"typeLabel":16,"stem":392,"options":393,"answer":181,"analysis":37},1106352,"关于路面修复作业的说法中，正确的有（ ）。",[394,396,398,400,402],{"key":20,"text":395,"correct":22},"坑槽必须三天内完成，若不能完成必须布置作业控制区",{"key":24,"text":397,"correct":26},"作业人员必须穿着有反光标志的橘红色工作装",{"key":28,"text":399,"correct":26},"在高速公路和一级公路上修复作业必须用车辆接送",{"key":31,"text":401,"correct":26},"在山体滑坡、塌方、泥石流等路段作业必须有专人观察险情",{"key":34,"text":403,"correct":26},"夜间作业，应设置照明设施",{"id":405,"libraryId":5,"type":15,"typeLabel":16,"stem":406,"options":407,"answer":181,"analysis":37},1106353,"监理工程师对施工现场实施监理工作中，发现施工单位有违反国家法规、标准、安全操作规程的行为，应及时制止并采取的措施有（ ）。",[408,410,412,414,416],{"key":20,"text":409,"correct":22},"专职安全生产管理人员督促及检查每天班组交底情况",{"key":24,"text":411,"correct":26},"发现严重冒险作业和严重安全事故隐患的，责令其暂时停工进行整改",{"key":28,"text":413,"correct":26},"下达隐患整改通知单，要求施工单位整改事故隐患，并复查整改结果情况",{"key":31,"text":415,"correct":26},"向建设单位报告督促施工单位整改情况",{"key":34,"text":417,"correct":26},"向工程所在地政府有关部门报告施工单位拒不整改或不停止施工情况",{"id":419,"libraryId":5,"type":15,"typeLabel":16,"stem":420,"options":421,"answer":52,"analysis":37},1106354,"日常安全监理实施程序包括（ ）。",[422,423,424,425,426],{"key":20,"text":367,"correct":26},{"key":24,"text":369,"correct":26},{"key":28,"text":371,"correct":26},{"key":31,"text":373,"correct":26},{"key":34,"text":427,"correct":22},"发出口头通知，开具罚款单",{"id":429,"libraryId":5,"type":15,"typeLabel":16,"stem":430,"options":431,"answer":305,"analysis":37},1106355,"施工项目的安全自检应由项目经理定期进行，安全自检的分类包括（ ）。",[432,434,436,438,440],{"key":20,"text":433,"correct":26},"日常性检查",{"key":24,"text":435,"correct":26},"专业性检查",{"key":28,"text":437,"correct":26},"季节性检查",{"key":31,"text":439,"correct":22},"定期检查",{"key":34,"text":441,"correct":26},"节假日前后的检查",{"id":443,"libraryId":5,"type":15,"typeLabel":16,"stem":444,"options":445,"answer":138,"analysis":37},1106356,"作业宜选择在交通量较小时段进行。作业前，应做好的工作有（ ）。",[446,448,450,452,454],{"key":20,"text":447,"correct":26},"检测隧道内CO、烟雾等有害气体的浓度",{"key":24,"text":449,"correct":22},"修复作业控制区经划定不得随意变更",{"key":28,"text":451,"correct":26},"检测结构状况是否会影响作业安全",{"key":31,"text":453,"correct":26},"检查施工信道信号灯是否准确、明显，施工标志设置是否规范",{"key":34,"text":455,"correct":26},"对养护机械、台架进行全面的安全检查",{"id":457,"libraryId":5,"type":15,"typeLabel":16,"stem":458,"options":459,"answer":470,"analysis":37},1106357,"弃方符合的规定描述错误的是（ ）",[460,462,464,466,468],{"key":20,"text":461,"correct":22},"弃土场四周应设立警示标志",{"key":24,"text":463,"correct":22},"“先支护、后弃土",{"key":28,"text":465,"correct":26},"水库、湖泊可弃方",{"key":31,"text":467,"correct":26},"桥墩台、涵洞口可弃方",{"key":34,"text":469,"correct":22},"弃方不得影响排洪、通航,不得加剧河岸冲刷","CD",{"id":472,"libraryId":5,"type":15,"typeLabel":16,"stem":473,"options":474,"answer":485,"analysis":37},1106358,"以下关于钢筋工程描述正确的是（ ）",[475,477,479,481,483],{"key":20,"text":476,"correct":22},"钢筋加工机械绝大多数转动部件应有防护罩",{"key":24,"text":478,"correct":26},"弯曲钢筋的作业半径内和机身不设固定销的一侧不得站人或通行",{"key":28,"text":480,"correct":26},"钢筋或牵引钢丝两侧3m内及冷拉线两端不得站人或通行",{"key":31,"text":482,"correct":22},"对焊作业闪光区四周无须设置挡板",{"key":34,"text":484,"correct":22},"可以单点起吊","BC",{"id":487,"libraryId":5,"type":15,"typeLabel":16,"stem":488,"options":489,"answer":52,"analysis":37},1106359,"储油罐的设置应符合下列规定（ ）。",[490,492,494,496,498],{"key":20,"text":491,"correct":26},"储油罐与在建工程的防火间距应不小于15m",{"key":24,"text":493,"correct":26},"储油罐顶部应设置遮阳棚",{"key":28,"text":495,"correct":26},"接地电阻不得大于10Ω",{"key":31,"text":497,"correct":26},"应悬挂醒目的禁止烟火等警示标识",{"key":34,"text":499,"correct":22},"需设置围墙",{"id":501,"libraryId":5,"type":15,"typeLabel":16,"stem":502,"options":503,"answer":514,"analysis":37},1106360,"关于安全带的使用，下列选项正确的有（ ）。",[504,506,508,510,512],{"key":20,"text":505,"correct":26},"安全带使用前应进行检查",{"key":24,"text":507,"correct":26},"安全带应高挂低用，并应扣牢在牢固的物体上",{"key":28,"text":509,"correct":22},"安全带的安全绳必须打结使用",{"key":31,"text":511,"correct":26},"安全带的各部件不得随意更换或拆除",{"key":34,"text":513,"correct":26},"安全绳有效长度不应大于2m","ABDE",{"id":516,"libraryId":5,"type":15,"typeLabel":16,"stem":517,"options":518,"answer":138,"analysis":37},1106361,"关于钢直梯的相关规定，下列选项中正确的有（ ）。",[519,521,523,525,527],{"key":20,"text":520,"correct":26},"攀登高度不宜大于8m",{"key":24,"text":522,"correct":22},"踏棍间距宜为0.5m",{"key":28,"text":524,"correct":26},"高度大于2m应设护笼，护笼间距宜为0.5m",{"key":31,"text":526,"correct":26},"高度大于8m应设梯间平台，并分段设梯",{"key":34,"text":528,"correct":26},"梯宽宜为0.6～1.1m",{"id":530,"libraryId":5,"type":15,"typeLabel":16,"stem":531,"options":532,"answer":138,"analysis":37},1106362,"关于模板、支架的拆除，下列选项正确的有（ ）。",[533,535,537,539,541],{"key":20,"text":534,"correct":26},"承重模板应横向同时、纵向对称均衡卸落",{"key":24,"text":536,"correct":22},"承重模板应纵向同时、横向对称均衡卸落",{"key":28,"text":538,"correct":26},"遵循先拆非承重模板、后拆承重模板的原则",{"key":31,"text":540,"correct":26},"遵循自上而下、分层分段拆除的顺序",{"key":34,"text":542,"correct":26},"模板存放应符合规定",{"id":544,"libraryId":5,"type":15,"typeLabel":16,"stem":545,"options":546,"answer":514,"analysis":37},1106363,"关于模板安装的相关规定，下列选项中正确的有（ ）。",[547,549,551,553,555],{"key":20,"text":548,"correct":26},"吊装模板前，应检查模板和吊点",{"key":24,"text":550,"correct":26},"模板安装就位后，应立即支撑和固定",{"key":28,"text":552,"correct":22},"基准面以上3m安装模板应搭设脚手架或施工平台",{"key":31,"text":554,"correct":26},"模板应按设计要求准确就位",{"key":34,"text":556,"correct":26},"模板安装完成后节点联系应牢固",{"id":558,"libraryId":5,"type":15,"typeLabel":16,"stem":559,"options":560,"answer":52,"analysis":37},1106364,"关于铺设电缆线的注意事项，下列选项正确的有（ ）。",[561,563,565,567,569],{"key":20,"text":562,"correct":26},"埋设电缆沟槽边缘的安全距离不得小于0.5m",{"key":24,"text":564,"correct":26},"地下埋设电缆应设防护管",{"key":28,"text":566,"correct":26},"架空铺设电缆应沿墙或电杆做绝缘固定",{"key":31,"text":568,"correct":26},"水上的岸电应用绝缘物架设，电缆线应留有余量",{"key":34,"text":570,"correct":22},"埋设电缆沟槽边缘的安全距离不得小于1m",{"id":572,"libraryId":5,"type":15,"typeLabel":16,"stem":573,"options":574,"answer":138,"analysis":37},1106365,"关于施工便道的相关规定，下列选项中正确的有（ ）。",[575,577,579,581,583],{"key":20,"text":576,"correct":26},"双车道施工便道宽度不宜小于6.5m",{"key":24,"text":578,"correct":22},"单车道施工便道宽度不宜小于6.5m",{"key":28,"text":580,"correct":26},"单车道施工便道宽度不宜小于4.5m",{"key":31,"text":582,"correct":26},"错车道路段的施工便道宽度不宜小于6.5m",{"key":34,"text":584,"correct":26},"施工便道应根据需要设置排水沟和圆管涵等排水设施",{"id":586,"libraryId":5,"type":15,"typeLabel":16,"stem":587,"options":588,"answer":514,"analysis":37},1106366,"关于隧道排水作业的相关规定，下列选项中正确的有（ ）。",[589,591,593,595,597],{"key":20,"text":590,"correct":26},"隧道内反坡排水方案应根据距离、坡度、水量和设备情况确定",{"key":24,"text":592,"correct":26},"隧道内顺坡排水沟断面应满足隧道排水需要",{"key":28,"text":594,"correct":22},"抽水机排水能力应大于排水量的30%",{"key":31,"text":596,"correct":26},"抽水机排水能力应大于排水量的20%",{"key":34,"text":598,"correct":26},"遇渗漏水面积突然增加，应立即停止施工",{"id":600,"libraryId":5,"type":15,"typeLabel":16,"stem":601,"options":602,"answer":305,"analysis":37},1106367,"明洞施工应满足的要求有（ ）。",[603,605,607,609,611],{"key":20,"text":604,"correct":26},"明洞开挖前，洞顶及四周应设防水、排水设施",{"key":24,"text":606,"correct":26},"开挖松软地层边、仰坡应随挖随支护",{"key":28,"text":608,"correct":26},"衬砌强度未达到设计的70%、防水层未完成时，不得回填",{"key":31,"text":610,"correct":22},"明洞应自下而上开挖",{"key":34,"text":612,"correct":26},"明洞槽不宜在雨天开挖",{"id":614,"libraryId":5,"type":15,"typeLabel":16,"stem":615,"options":616,"answer":627,"analysis":37},1106368,"潜水员水下安装构件必须满足的要求有（ ）。",[617,619,621,623,625],{"key":20,"text":618,"correct":22},"不得在沉井刃脚下或护筒底口以下作业",{"key":24,"text":620,"correct":26},"潜水员应在构件基本就位和稳定后靠近待安装构件",{"key":28,"text":622,"correct":26},"供气管不得置于构件缝中",{"key":31,"text":624,"correct":22},"沉井和大直径护筒内侧水位应高于外侧水位",{"key":34,"text":626,"correct":26},"使用专用工具调整构件的安装位置","BCE",{"id":629,"libraryId":5,"type":15,"typeLabel":16,"stem":630,"options":631,"answer":305,"analysis":37},1106369,"下列关于爆破法破碎冻土应当注意的安全事项，说法正确的有（ ）。",[632,634,636,638,640],{"key":20,"text":633,"correct":26},"爆破施工要离建筑物50m以外，距离高压电线200m以外",{"key":24,"text":635,"correct":26},"爆破工作应有技术安全措施，并经主管部门批准",{"key":28,"text":637,"correct":26},"放炮后要经过20min才可以前往检查",{"key":31,"text":639,"correct":22},"爆破施工要离建筑物100m以外，距离高压电线200m以外",{"key":34,"text":641,"correct":26},"冬季施工不得使用硝化甘油类炸药",{"id":643,"libraryId":5,"type":15,"typeLabel":16,"stem":644,"options":645,"answer":81,"analysis":37},1106370,"经审批的水土保持方案，如（ ） 发生变化，应及时修改方案，并报原审批单位审批。",[646,648,650,652,654],{"key":20,"text":647,"correct":26},"项目性质",{"key":24,"text":649,"correct":26},"规模",{"key":28,"text":651,"correct":26},"地点",{"key":31,"text":653,"correct":22},"名称",{"key":34,"text":655,"correct":22},"公司股权变化",{"id":657,"libraryId":5,"type":15,"typeLabel":16,"stem":658,"options":659,"answer":52,"analysis":37},1106371,"《中华人民共和国环境保护法修订案》明确了环境保护应坚持（ ）的原则。",[660,662,664,666,668],{"key":20,"text":661,"correct":26},"保护优先",{"key":24,"text":663,"correct":26},"预防为主",{"key":28,"text":665,"correct":26},"综合治理",{"key":31,"text":667,"correct":26},"公众参与",{"key":34,"text":669,"correct":22},"政府主导",{"id":671,"libraryId":5,"type":15,"typeLabel":16,"stem":672,"options":673,"answer":52,"analysis":37},1106372,"2014年交通运输部提出了（ ）的发展战略决策。",[674,676,678,680,682],{"key":20,"text":675,"correct":26},"综合交通",{"key":24,"text":677,"correct":26},"智慧交通",{"key":28,"text":679,"correct":26},"绿色交通",{"key":31,"text":681,"correct":26},"平安交通",{"key":34,"text":683,"correct":22},"经济交通",{"id":685,"libraryId":5,"type":15,"typeLabel":16,"stem":686,"options":687,"answer":52,"analysis":37},1106373,"以下关于水土保持方案，正确的有（ ） A.建设项目水土保持方案文件分为水土保持方案报告书和水土保护方案报告表。",[688,690,692,694,696],{"key":20,"text":689,"correct":26},"凡征占地面积在即10000m2以上，应当编报水土保持方案报告书",{"key":24,"text":691,"correct":26},"挖填土石方总量在10000m3以上的开发建设项目，应当编报水土保持方案报告书",{"key":28,"text":693,"correct":26},"除",{"key":31,"text":695,"correct":26},"C外，其他开发建设项目应当编报水土保持方案报告表。",{"key":34,"text":697,"correct":22},"公路建设项目应编制水土保护方案报告表书。",{"id":699,"libraryId":5,"type":15,"typeLabel":16,"stem":700,"options":701,"answer":52,"analysis":37},1106374,"绿色公路建设的专项行动包括（ ）。",[702,704,706,708,710],{"key":20,"text":703,"correct":26},"着力实现“零弃方、少借方\"",{"key":24,"text":705,"correct":26},"实施改扩建工程绿色升级",{"key":28,"text":707,"correct":26},"积极应用建筑信息模型（BIM）新技术",{"key":31,"text":709,"correct":26},"推进绿色服务区建设",{"key":34,"text":711,"correct":22},"大力发展干线公路",{"id":713,"libraryId":5,"type":15,"typeLabel":16,"stem":714,"options":715,"answer":52,"analysis":37},1106375,"绿色公路建设的“四大要素”（ ）是推动绿色公路建设的关键。",[716,718,720,722,724],{"key":20,"text":717,"correct":26},"资源节约",{"key":24,"text":719,"correct":26},"生态环保",{"key":28,"text":721,"correct":26},"节能高效",{"key":31,"text":723,"correct":26},"服务提升",{"key":34,"text":725,"correct":22},"创新发展",[727,731,734,737,740,743],{"id":728,"name":729,"category":7,"favorite":730},1,"领导干部任职前廉政法规知识测试题",92,{"id":732,"name":733,"category":7,"favorite":728},595,"建筑结构与设备",{"id":735,"name":736,"category":7,"favorite":728},715,"招标采购专业知识与法律法规",{"id":738,"name":739,"category":7,"favorite":728},848,"市政方向-通用基础",{"id":741,"name":742,"category":7,"favorite":8},534,"BIM工程师",{"id":744,"name":742,"category":7,"favorite":8},535]