[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106370":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106370,781,2,"多选题","经审批的水土保持方案，如（ ） 发生变化，应及时修改方案，并报原审批单位审批。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目性质",true,{"key":16,"text":17,"correct":14},"B","规模",{"key":19,"text":20,"correct":14},"C","地点",{"key":22,"text":23,"correct":24},"D","名称",false,{"key":26,"text":27,"correct":24},"E","公司股权变化","ABC","经审批的水土保持方案，如项目性质、规模、地点等发生变化，应及时修改方案，并报原审批单位审批。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]