[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106354":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106354,781,2,"多选题","日常安全监理实施程序包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","发出口头通知，开具整改通知单",true,{"key":16,"text":17,"correct":14},"B","召开专题监理例会",{"key":19,"text":20,"correct":14},"C","签发工程停工令",{"key":22,"text":23,"correct":14},"D","向建设主管部门报告",{"key":25,"text":26,"correct":27},"E","发出口头通知，开具罚款单",false,"ABCD","日常安全监理实施程序包括：①发出口头通知，开具整改通知单。在日常的现场巡视、检查工作中，若发现存在违反强制性建设标准的现象，或安全事故隐患，应首先口头通知施工方，要求立即采取整改措施，并及时采用书面通知予以确认；②召开专题监理例会。当签发书面通知、指令后，仍未采取及时整改时，应当组织建设单位、施工单位及其他有关单位召开专题监理例会，对书面通知、指令中的内容，结合强制性建设标准加以强调；③签发工程停工令。在签发书面通知、指令或召开专题例会后，仍未及时整改，或拒不整改，情况严重的，应当要求施工方暂时停止施工，并由总监签发工程停工令，同时报告建设单位；④向建设主管部门报告。若施工单位拒不整改或者不停止施工的，总监理工程师应及时向有关交通主管部门以书面形式报告。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]