[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106335":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106335,781,2,"多选题","下列选项中，属于在充分分析工程风险因素、事故起因、救援经过的基础上，重点评估以下内容的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","邀请专家协助开展评估",false,{"key":16,"text":17,"correct":18},"B","预防预警和预控措施",true,{"key":20,"text":21,"correct":18},"C","信息报送的时效性与准确性",{"key":23,"text":24,"correct":18},"D","事故救援组织机构设置及运行",{"key":26,"text":27,"correct":18},"E","技术方案及实施情况","BCDE","在充分分析工程风险因素、事故起因、救援经过的基础上，重点评估以下内容：①预防预警和预控措施；②项目应急自救效果及能力；③信息报送的时效性与准确性；④事故救援组织机构设置及运行；⑤现场救援决策、指挥、协调机制及效率；⑥技术方案及实施情况；⑦应急协作及应急保障。A项属于评估程序。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]