[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106297":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106297,781,2,"多选题","根据监理措施采取的时间进行分类，则费用监理分类包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","纵向监理",false,{"key":16,"text":17,"correct":18},"B","前馈监理",true,{"key":20,"text":21,"correct":18},"C","过程监理",{"key":23,"text":24,"correct":18},"D","反馈监理",{"key":26,"text":27,"correct":14},"E","横向监理","BCD","费用监理的方法很多，从监理措施采取的时间不同分类，可以将费用监理分为事前监理（前馈监理）、事中监理（过程监理）、事后监理（反馈监理）三类：①事前监理。也称前馈控制、主动控制，是指在发生目标偏差以前，即在实际工程费用超过合同价格之前，根据预测的信息，采取相应的预防措施予以调节，使工程费用不偏离或尽量少偏离合同价；②事中监理。也称过程控制、跟踪监理，是指监理人员跟踪施工过程，并对其进行监理的一种监理方法；③事后监理。也称反馈控制、被动控制，是指监理人员将监理信息输送出去后又把作用结果返送回来，并对信息的再输出发生影响，以起到监理的作用。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]