[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106294":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106294,781,2,"多选题","延期评估应主要从以下哪些方面进行评定？（ ）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工单位提交的申请资料必须真实、齐全，满足评审需要",true,{"key":16,"text":17,"correct":14},"B","申请延期的合同依据必须准确",{"key":19,"text":20,"correct":14},"C","申请延期的理由必须正确与充分",{"key":22,"text":23,"correct":24},"D","申请延期的主要负责人必须中层管理以上职位",false,{"key":26,"text":27,"correct":14},"E","申请延期天数的计算原则与方法应恰当","ABCE","延期评估应主要从以下几个方面进行评定：①施工单位提交的申请资料必须真实、齐全，满足评审需要。②申请延期的合同依据必须准确。③申请延期的理由必须正确与充分。④申请延期天数的计算原则与方法应恰当。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]