[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106293":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106293,781,2,"多选题","施工进度计划的实施保证，从内容上可概括为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","组织保证",true,{"key":16,"text":17,"correct":18},"B","质量保证",false,{"key":20,"text":21,"correct":14},"C","技术保证",{"key":23,"text":24,"correct":14},"D","合同保证",{"key":26,"text":27,"correct":18},"E","安全保证","ACD","施工进度计划的实施保证，从内容上可概括为组织保证、技术保证、合同保证、经济保证。从工程项目建设的参与方来分，有施工、监理和建设单位。在施工监理过程中，对于监理工程师来说，主要是落实好施工和监理单位进度计划实施保证系统。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]