[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106289":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106289,781,2,"多选题","（ ）会影响建设施工进度。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实际到达现场的施工机械型号、数量和到达日期，是否与计划一致",true,{"key":16,"text":17,"correct":18},"B","施工现场人员的装备是否安全",false,{"key":20,"text":21,"correct":14},"C","施工单位技术和施工人员的到达情况",{"key":23,"text":24,"correct":14},"D","建设单位提供现场、通道的时间对工程施工有无影响",{"key":26,"text":27,"correct":14},"E","各分项工程开工、完工时间及进展情况","ACDE","影响施工进度的相关内容： ①实际到达现场的施工机械型号、数量和到达日期，是否与计划一致； ②施工单位技术和施工人员的到达情况； ③当地劳务人员、施工所需材料是否已按时解决； ④建设单位提供现场、通道的时间对工程施工有无影响； ⑤各分项工程开工、完工时间及进展情况； ⑥施工机械运转的实际效率如何，是否满足计划指标； ⑦延误的情况和原因； ⑧有关进度的口头或书面指令情况； ⑨与修订进度计划有直接关系的资料； ⑩施工现场发生的与进度有关的其他事件。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]