[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106288":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106288,781,2,"多选题","某工程双代号时标网络计划执行到第6周末和第11周末时，检查其实际进度如下图前锋线所示，检查结果表明（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","第6周末检查时，工作A拖后1周，不影响总工期",false,{"key":16,"text":17,"correct":14},"B","第6周末检查时，工作E提前1周，不影响总工期",{"key":19,"text":20,"correct":14},"C","第6周末检查时，工作C提前1周，预计总工期缩短1周",{"key":22,"text":23,"correct":24},"D","第11周末检查时，工作G拖后1周，不影响总工期",true,{"key":26,"text":27,"correct":24},"E","第11周末检查时，工作H提前1周，预计总工期缩短1周","DE","本题考查的是进度监理与进度检查。选项A项中第六周末检查时，工作A拖后2周，影响总工期；选项B项中工作E提前2周，影响总工期；选项C项中工作C工作提前1周，不影响总工期。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]