[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106287":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106287,781,2,"多选题","在承包人提交的工程总体进度计划中，应当反映出（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","完成各单位工程及各施工阶段所需要的工期、最早开始和最迟结束的时间",true,{"key":16,"text":17,"correct":14},"B","各单位工程及各施工阶段需要完成的工程量及现金流动估算",{"key":19,"text":20,"correct":14},"C","工程施工项目的合同工期",{"key":22,"text":23,"correct":14},"D","各单位工程或分部工程的施工方案和施工组织设计",{"key":25,"text":26,"correct":27},"E","总体工程量大小",false,"ABCD","在承包人提交的工程总体进度计划中，应当反映出以下主要内容：①工程施工项目的合同工期，即合同工期或指令工期；②完成各单位工程及各施工阶段所需要的工期、最早开始和最迟结束的时间；③各单位工程及各施工阶段需要完成的工程量及现金流动估算；④各单位工程及各施工阶段所需配备的人力和设备数量；⑤各单位工程或分部工程的施工方案和施工组织设计等。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]