[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106285":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106285,781,2,"多选题","年度进度计划的主要作用有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","统一安排全年内各正在施工或将要开工工程的施工",true,{"key":16,"text":17,"correct":18},"B","确定（季）月施工任务",false,{"key":20,"text":21,"correct":14},"C","根据年度季节、气候的不同，合理安排施工进度",{"key":23,"text":24,"correct":14},"D","确定各项年度生产指标",{"key":26,"text":27,"correct":18},"E","进行月施工各项指标的平衡、汇总","ACD","年度进度计划的主要作用。 ①统一安排全年内各正在施工或将要开工工程的施工，确定年度施工任务。 ②确定各项年度生产指标，即在年度内要完成哪些单位工程，分部、分项工程或部分完成哪些工程项目。 ③根据年度季节、气候的不同，合理安排施工进度。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]