[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106283":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106283,781,2,"多选题","关键工程进度计划中应反映的内容有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","具体施工方案和施工方法",true,{"key":16,"text":17,"correct":14},"B","完成关键工程进度计划的保证措施",{"key":19,"text":20,"correct":14},"C","总体进度计划及各道工序的控制日期",{"key":22,"text":23,"correct":24},"D","固定资产估算",false,{"key":26,"text":27,"correct":14},"E","各施工阶段的人力、设备和材料的配额及运转安排","ABCE","关键工程进度计划中应反映的内容有：①具体施工方案和施工方法；②总体进度计划及各道工序的控制日期；③现金流动估算；④各施工阶段的人力、设备和材料的配额及运转安排；⑤施工准备及结束清场的时间安排；⑥对总体进度计划及其他相关工程的控制、依赖关系和说明；⑦完成关键工程进度计划的保证措施。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]