[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106282":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106282,781,2,"多选题","安排各个工程项目或工作（序）的方法主要有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","顺行法",true,{"key":16,"text":17,"correct":14},"B","逆算法",{"key":19,"text":20,"correct":21},"C","突出法",false,{"key":23,"text":24,"correct":21},"D","插入法",{"key":26,"text":27,"correct":14},"E","重点法","ABE","为了在工期内完成整个工程，应根据实际经验，将各个项目所需时间在总工期内进行分配，作出符合实际情况的进度计划。通常使用顺行法、逆算法和重点法来进行这样的安排。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]