[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106281":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106281,781,2,"多选题","以下属于时间优化途径的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","将连续施工的工作改为平行作业",true,{"key":16,"text":17,"correct":14},"B","将顺序作业调整为流水作业",{"key":19,"text":20,"correct":14},"C","缩短关键工作的持续时间",{"key":22,"text":23,"correct":24},"D","相应地缩短非关键工作的持续时间",false,{"key":26,"text":27,"correct":24},"E","增加资源","ABC","时间优化途径包括：①将连续施工的工作改为平行作业。②将顺序作业调整为流水作业。③缩短关键工作的持续时间。④相应地延长非关键工作的持续时间。⑤从计划外增加资源。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]