[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106279":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106279,781,2,"多选题","削峰填谷优化步骤包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计算网络计划节点时间参数，确定关键线路",true,{"key":16,"text":17,"correct":18},"B","计算工作6个时间参数",false,{"key":20,"text":21,"correct":14},"C","按节点最早时间绘时标图",{"key":23,"text":24,"correct":18},"D","绘制双代号网络图",{"key":26,"text":27,"correct":14},"E","运用削峰填谷法原理","ACE","削峰填谷优化步骤包括：第一步计算网络计划节点时间参数，确定关键线路；第二步按节点最早时间绘时标图；第三步运用削峰填谷法原理。以削低整个计划的资源高峰为目的，调整位于高峰时段的非关键工作，按优先推迟原则循环进行，逐步实现资源均衡。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]