[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106276":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106276,781,2,"多选题","被选作压缩的各项工作应满足（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","必须是关键线路上的工作",true,{"key":16,"text":17,"correct":14},"B","该工作的持续时间不短于其最短工期",{"key":19,"text":20,"correct":21},"C","工作持续时间最长",false,{"key":23,"text":24,"correct":14},"D","它的成本斜率是关键线路上可压缩工作中的最小值",{"key":26,"text":27,"correct":21},"E","不是主体工程部分的工作","ABD","被选作压缩的各项工作应满足下列条件：①必须是关键线路上的工作；②该工作的持续时间不短于其最短工期；③它的成本斜率是关键线路上可压缩工作中的最小值。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]