[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106275":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106275,781,2,"多选题","项目实际工程进度计划的优化，只能根据具体条件进行单项指标优化，具体的优化是指（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","时间优化条件是资源有限、工期最短",true,{"key":16,"text":17,"correct":18},"B","时间优化条件是成本有限、工期最短",false,{"key":20,"text":21,"correct":14},"C","成本优化条件为工期限定、成本最低",{"key":23,"text":24,"correct":18},"D","成本优化条件为资源限定、成本最低",{"key":26,"text":27,"correct":14},"E","资源优化条件为工期限定、资源均衡","ACE","本题考查的是网络计划的时间优化。时间优化条件是资源有限、工期最短；成本优化条件为工期限定、成本最低；资源优化条件则为工期限定、资源均衡。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]