[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106271":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106271,781,2,"多选题","以下属于控制性时间参数的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","ES",true,{"key":16,"text":17,"correct":14},"B","LS",{"key":19,"text":20,"correct":21},"C","TF",false,{"key":23,"text":24,"correct":14},"D","LT",{"key":26,"text":27,"correct":14},"E","ET","ABDE","控制性时间参数包括：①最早时间系列参数包括：工作的最早可能开始时间（ES）；工作的最早可能完成时间（EF）；节点的最早可能实现时间（ET）。②最迟时间系列参数包括：工作的最迟必须开始时间（LS）；工作的最迟必须完成时间（LF）；节点的最迟必须实现时间（LT）。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]