[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106268":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106268,781,2,"多选题","通常的工作关系表的基本内容包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工作代号",true,{"key":16,"text":17,"correct":14},"B","工作名称",{"key":19,"text":20,"correct":14},"C","紧前工作",{"key":22,"text":23,"correct":14},"D","持续时间",{"key":25,"text":26,"correct":27},"E","延迟时间",false,"ABCD","工作项目及其间的关系、持续时间等确定之后，应将这些资料填写到工作关系表中去。通常的工作关系表的基本内容包括：①工作代号；②工作名称；③紧前工作（或紧后工作）；④持续时间等。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]