[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106267":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106267,781,2,"多选题","时间坐标网络计划图的绘制方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","按节点最早可能实现时间",true,{"key":16,"text":17,"correct":14},"B","按节点最迟必须实现时间",{"key":19,"text":20,"correct":21},"C","按工作最早结束时间",false,{"key":23,"text":24,"correct":14},"D","按优化时间",{"key":26,"text":27,"correct":21},"E","按工作最迟结束时间","ABD","时间坐标网络计划图的绘制方法有3种，即按节点最早可能实现时间（节点最早时间）、节点最迟必须实现时间（节点最迟时间）、优化时间直接绘制。前两种方法主要用于网络计划分析和资源优化，所以应用较广；后一种方法只适用于工程项目中工作数目较少、工艺过程较简单的进度网络计划，因此实际应用较少。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]