[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106266":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106266,781,2,"多选题","某工程双代号网络计划中各节点的最早时间与最迟时间如图10-2-5所示，图中表明（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作1-4为关键工作",false,{"key":16,"text":17,"correct":18},"B","工作4-7为关键工作",true,{"key":20,"text":21,"correct":18},"C","工作1-3的自由时差为0",{"key":23,"text":24,"correct":18},"D","工作3-7的总时差为3",{"key":26,"text":27,"correct":14},"E","关键线路有3条","BCD","在网络计划中，总时差最小的工作为关键工作。当网络计划的计划工期等于计算工期时，总时差为零的工作就是关键工作。黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com本网络计划的关键线路有两条：即①→②→⑤→⑧和①→②→④→⑦→⑧，总工期为16。工作1-4的自由时差与总时差均为：4－2＝2，为非关键工作；工作1-3的自由时差为：3－3＝0，总时差为1，为非关键工作；工作3-7的自由时差与总时差均为：10－3－4＝3，为非关键工作。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]