[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106265":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106265,781,2,"多选题","某工程双代号网络计划如图10-2-2所示，图中已标明每项工作的最早开始时间和最迟开始时间，该计划表明（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作1-3的自由时差为2",true,{"key":16,"text":17,"correct":14},"B","工作2-5为关键工作",{"key":19,"text":20,"correct":21},"C","工作2-4的自由时差为1",false,{"key":23,"text":24,"correct":14},"D","工作3-6的总时差为零",{"key":26,"text":27,"correct":21},"E","工作4-7为关键工作","ABD","如图所示，工作1-3的自由时差＝4－0－2＝2；图中的关键线路为：①→②→⑤→⑦，①→②→③→⑥→⑦，工作2-5为关键工作，工作4-7为非关键工作；工作2-4的自由时差＝min（13－4－7），（11－4－7），（12－4－7）]＝0；工作3-6的总时差＝12－4－8＝0。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]