[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106263":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106263,781,2,"多选题","某工程双代号时标网络计划如图10-3-2所示，该计划表明（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作C的自由时差为2天",true,{"key":16,"text":17,"correct":18},"B","工作E的最早开始时间为第4天",false,{"key":20,"text":21,"correct":14},"C","工作D为关键工作",{"key":23,"text":24,"correct":18},"D","工作H的总时差为零",{"key":26,"text":27,"correct":18},"E","工作B的最迟完成时间为第1天","AC","工作的自由时差是指在不影响其紧后工作最早开始时间的前提下，本工作可以利用的机动时间；工作的总时差是指在不影响总工期的前提下，本工作可以利用的机动时间。由图知C工作的自由时差为2天，E工作的最早开始时间为第2天，D为关键线路上的关键工作，持续时间为3天，工作H的总时差为1天，工作B的最迟完成时间为第2天。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]