[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106262":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106262,781,2,"多选题","某工程双代号时标网络计划如图10-2-3所示，该计划表明（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","G工作为关键工作",true,{"key":16,"text":17,"correct":18},"B","E工作的总时差为3天",false,{"key":20,"text":21,"correct":14},"C","B工作的总时差为1天",{"key":23,"text":24,"correct":18},"D","F工作为关键工作",{"key":26,"text":27,"correct":14},"E","C工作的总时差为2天","ACE","该工程双代号时标网络计划的关键路线有两条：A→D→G→I或A→D→G→J。则G工作是关键工作；F工作是非关键工作；B工作的总时差为1天；C工作的总时差是2天；E工作的总时差是2天。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]