[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106261":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106261,781,2,"多选题","某分部工程双代号网络图如图10-2-4所示，图中错误有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多个终点节点",true,{"key":16,"text":17,"correct":18},"B","多个起点节点",false,{"key":20,"text":21,"correct":18},"C","工作代号重复",{"key":23,"text":24,"correct":14},"D","节点编号有误",{"key":26,"text":27,"correct":14},"E","存在循环回路","ADE","A项，终点节点有⑦⑧两个；B项，起点节点只有①一个；C项，工作代号重复没有重复；D项，②③④的节点编号有误；E项，③④⑥组成了循环回路。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]