[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106260":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106260,781,2,"多选题","某单位工程双代号网络计划如图10-1-2所示，图中错误有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多个起点节点",true,{"key":16,"text":17,"correct":18},"B","多个终点节点",false,{"key":20,"text":21,"correct":18},"C","存在多余虚工作",{"key":23,"text":24,"correct":14},"D","节点编号有误",{"key":26,"text":27,"correct":18},"E","存在循环回路","AD","在绘制双代号网络图时，一般应遵循以下基本规则：①网络图必须按照已定的逻辑关系绘制；②网络图中严禁出现从一个节点出发，顺箭头方向又回到原出发点的循环回路；③网络图中的箭线（包括虚箭线）应保持自左向右的方向，不应出现箭头指向左方的水平箭线和箭头偏向左方的斜向箭线；④网络图中严禁出现双向箭头和无箭头的连线；⑤网络图中严禁出现没有箭尾节点的箭线和没有箭头节点的箭线；⑥严禁在箭线上引入或引出箭线；⑦应尽量避免网络图中工作箭线的交叉；⑧网络图中应只有一个起点节点和一个终点节点（任务中部分工作需要分期完成的网络计划除外）。本题中存在①和②两个起始点以及从⑦→⑥的节点编号错误。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]