[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106259":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106259,781,2,"多选题","关于单代号网络图特点的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","单代号网络图的绘制方法比较复杂",false,{"key":16,"text":17,"correct":18},"B","各项工作的相互关系容易表达",true,{"key":20,"text":21,"correct":18},"C","不存在虚工作",{"key":23,"text":24,"correct":18},"D","便于检查",{"key":26,"text":27,"correct":18},"E","便于修改","BCDE","通过单代号网络图与双代号网络图的比较可以看出，单代号网络图的绘制方法比较简单，图中各项工作的相互关系容易表达，不存在虚工作，使得单代号网络图便于检查与修改。但是单代号网络图不能绘制成时标图，而双代号网络图可绘成时标图，特别是双代号网络图按节点最早时间绘制时标图时，可以清楚地反映出工作的局部时差，所以进行进度计划下达和对网络计划优化时，经常采用双代号网络计划图。由于双代号网络图和单代号网络图各有优缺点，因此两种形式的网络计划图的应用都很普遍。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]