[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106258":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106258,781,2,"多选题","单代号网络计划图绘制方法包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","前进法",true,{"key":16,"text":17,"correct":18},"B","精细法",false,{"key":20,"text":21,"correct":14},"C","后退法",{"key":23,"text":24,"correct":18},"D","先节点后箭线",{"key":26,"text":27,"correct":14},"E","先粗后细法","ACE","绘制单代号网络计划图的方法，也可采用前进法、后退法和先粗后细法。项目工程进度计划实际应用中，主要采用先粗后细法绘制单代号网络图；确定工作之间的相互关系表后，多数采用前进法或后退法绘制单代号网络图。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]