[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106257":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106257,781,2,"多选题","按照时差的不同性质和作用。可以分为工作的（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","自由时差",false,{"key":16,"text":17,"correct":18},"B","总时差",true,{"key":20,"text":21,"correct":18},"C","局部时差",{"key":23,"text":24,"correct":18},"D","干涉时差",{"key":26,"text":27,"correct":18},"E","独立时差","BCDE","按照时差的不同性质和作用。可以分为工作的总时差，局部时差，干涉时差和独立时差等。根据前面所介绍的节点时间参数和工作时间参数计算结果，可以计算网络计划图中各项工作的各类时差。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]