[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106256":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106256,781,2,"多选题","在下图所示的网络计划中，有关各项工作的总时差和自由时差的表述正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作A的自由时差为0，总时差为2",false,{"key":16,"text":17,"correct":14},"B","工作B的总时差和自由时差均为1",{"key":19,"text":20,"correct":21},"C","工作C的总时差和自由时差均为2",true,{"key":23,"text":24,"correct":21},"D","工作D的自由时差为0，总时差为1",{"key":26,"text":27,"correct":21},"E","工作E的自由时差和总时差均为0","CDE","本题考查的是时间坐标网络计划。选项A错误，工作A的自由时差为0，总时差为4；选项B错误，工作B的自由时差为0，总时差为1。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]