[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106255":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106255,781,2,"多选题","某分部工程双代号网络计划如下图所示，图中的错误有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作代号重复",false,{"key":16,"text":17,"correct":18},"B","节点编号有误",true,{"key":20,"text":21,"correct":14},"C","多个起点节点",{"key":23,"text":24,"correct":18},"D","多个终点节点",{"key":26,"text":27,"correct":14},"E","存在循环回路","BD","本题考查的是双代号网络计划图的绘制。（1）节点8、9指向，节点编号错误。 （2）节点8、10均为终点，存在多个终点节点。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]