[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106253":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106253,781,2,"多选题","某分部工程中各项工作间逻辑关系见下表，相应的双代号网络计划如下图所示，图中错误有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多个终点节点",false,{"key":16,"text":17,"correct":18},"B","多个起点节点",true,{"key":20,"text":21,"correct":14},"C","工作代号重复",{"key":23,"text":24,"correct":18},"D","不符合给定逻辑关系",{"key":26,"text":27,"correct":18},"E","节点编号有误","BDE","本题考查的是双代号网络计划图的绘制。1、2均为起点节点。G的紧后仅有J，不符合给定逻辑关系。节点6、5指向，节点编号错误。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]