[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106242":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106242,781,2,"多选题","流水施工组织原则包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","根据工程项目对象划分施工段",true,{"key":16,"text":17,"correct":14},"B","划分工序并编工艺流程，且按工艺原则建立专业班组",{"key":19,"text":20,"correct":14},"C","各专业班组依次、连续进入各个施工段，完成同类工种的作业",{"key":22,"text":23,"correct":14},"D","计算或确定流水作业参数",{"key":25,"text":26,"correct":27},"E","相邻施工段及相邻工序尽可能衔接宽松",false,"ABCD","流水施工组织原则。 ①根据工程项目对象划分施工段； ②划分工序并编工艺流程，且按工艺原则建立专业班组； ③各专业班组依次、连续进入各个施工段，完成同类工种的作业； ④计算或确定流水作业参数； ⑤相邻施工段及相邻工序尽可能衔接紧密。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]