[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106240":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106240,781,2,"多选题","横道图的不足表现有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","不容易看出工作之间的相互依赖",true,{"key":16,"text":17,"correct":14},"B","无法反映工作的机动使用时间",{"key":19,"text":20,"correct":14},"C","不能实现定量分析",{"key":22,"text":23,"correct":24},"D","不能清楚了解工艺之间的逻辑关系",false,{"key":26,"text":27,"correct":14},"E","计算执行过程中实施计划偏离原计划时，只能进行局部简单的调整","ABCE","横道图编制施工进度计划的优点为：简单、形象、明了、直观、易懂，且便于检查和计算资源用量。它的不足表现在：①不容易看出工作之间的相互依赖、相互制约的关系，仅反映工作之间的前后衔接关系；②无法反映工作的机动使用时间，反映不出关键工作及哪些工作决定总工期；③不能实现定量分析，因而无法采用计算机计算；④计算执行过程中实施计划偏离原计划时，只能进行局部简单的调整；⑤无法进行施工组织及施工技术方案的比较与优化。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]