[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106234":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106234,781,2,"多选题","单位、分部及分项工程施工中，按施工工艺的特点和施工组织的要求，可将施工过程进一步分解为（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","综合过程",true,{"key":16,"text":17,"correct":14},"B","操作过程",{"key":19,"text":20,"correct":14},"C","工序",{"key":22,"text":23,"correct":14},"D","操作",{"key":25,"text":26,"correct":27},"E","流水能力",false,"ABCD","本题考查的是公路工程施工组织方法和特点。按施工工艺的特点和施工组织的要求，可将施工过程进一步分解为综合过程、操作过程、工序、操作、动作等",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]