[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106233":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106233,781,2,"多选题","下列关于全等节拍流水施工特点的说法中，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","所有施工过程在各个施工段上的流水节拍均相等",true,{"key":16,"text":17,"correct":18},"B","相邻专业工作队之间的流水步距不尽相等",false,{"key":20,"text":21,"correct":14},"C","专业工作队的数量等于施工过程的数量",{"key":23,"text":24,"correct":14},"D","各施工段之间没有空闲时间",{"key":26,"text":27,"correct":18},"E","流水施工工期等于施工段数与流水节拍的乘积","ACD","本题考查的是公路工程施工组织方法和特点。稳定流水也称为全等节拍流水，是指各道工序的流水节拍在各个施工段上完全相等，且工序之间的流水节拍也完全相等。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]