[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106232":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106232,781,2,"多选题","在组织流水作业时，确定流水节拍应考虑的因素有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","所采用的施工方法和施工机械",true,{"key":16,"text":17,"correct":18},"B","相邻两个施工过程相继开始施工的最小间隔时间",false,{"key":20,"text":21,"correct":18},"C","施工段数目",{"key":23,"text":24,"correct":14},"D","在工作面允许的前提下投入的劳动量和机械台班数量",{"key":26,"text":27,"correct":14},"E","专业工作队的工作班次","ADE","本题考查的是公路工程施工组织方法和特点。同一施工过程的流水节拍，主要由所采用的施工方法、施工机械以及在工作面允许的前提下投入施工的工人数、机械台班和采用的工作班次等因素确定。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]