[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106226":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106226,781,2,"多选题","工程变更一般可归纳为（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","因设计不合理而引起的工程变更",true,{"key":16,"text":17,"correct":14},"B","为优化设计方案而出现的工程变更",{"key":19,"text":20,"correct":21},"C","因承包人风险或监理人责任等原因而引起的工程变更",false,{"key":23,"text":24,"correct":14},"D","为满足地方政府的要求而不得不进行的工程变更",{"key":26,"text":27,"correct":14},"E","因承包人的施工质量事故而引起的工程变更","ABDE","按引发的原因不同，工程变更一般可归纳为如下几种情况：①因设计不合理而引起的工程变更；②发包人想扩大工程规模、提高设计标准或加快施工进度而出现的工程变更；③为满足地方政府的要求而不得不进行的工程变更；④为优化设计方案而出现的工程变更；⑤因发包人风险或监理人责任等原因而引起的工程变更；⑥因承包人的施工质量事故而引起的工程变更。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]