[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106225":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106225,781,2,"多选题","发包人违约的情形包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人未能按期开工",false,{"key":16,"text":17,"correct":18},"B","发包人原因造成停工的",true,{"key":20,"text":21,"correct":18},"C","发包人无法继续履行合同的",{"key":23,"text":24,"correct":18},"D","发包人无正当理由不按时返还工人工资保证金的",{"key":26,"text":27,"correct":18},"E","发包人不履行合同约定其他义务的","BCDE","在履行合同过程中发生的下列情形，属发包人违约：①发包人未能按合同约定支付预付款或合同价款，或拖延、拒绝批准付款申请和支付凭证，导致付款延误的；②发包人原因造成停工的；③监理人无正当理由没有在约定期限内发出复工指示，导致承包人无法复工的；④发包人无法继续履行或明确表示不履行或实质上已停止履行合同的；⑤发包人无正当理由不按时返还履约保证金、质量保证金或工人工资保证金的；⑥发包人不履行合同约定其他义务的。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]