[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106214":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106214,781,2,"多选题","工程量的计量方法包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","凭据法",true,{"key":16,"text":17,"correct":14},"B","均摊法",{"key":19,"text":20,"correct":21},"C","远程断面测量计算法",false,{"key":23,"text":24,"correct":14},"D","图纸计算法",{"key":26,"text":27,"correct":14},"E","现场点数计算法","ABDE","工程量的计量方法，一般有以下几种：①凭据法。如工程量清单第100章的保险费等。②均摊法。如工程量清单第100章的“总价子目”应按照合同约定的阶段性目标分解表进行分解计量，一般采用按月均摊的方法计量，如竣工文件费、承包人驻地建设和施工标准化费用等项目。③图纸计算法。对于钢筋混凝土结构物的钢筋、钻孔灌注桩的桩长、路面工程的铺筑面积等，一般采用图纸计算法。④现场断面测量计算法。如路基土石方开挖和填筑工程的计量需要现场断面测量计算法。⑤现场点数计算法。如场地清理的砍伐树木按照“棵”计数，桥梁的盆式支座按照“个”计数，道路交通标志按照“个”计数，计日工按现场记录的“工日”计算等。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]