[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106207":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106207,781,2,"多选题","以下的计量的说法中，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","任何工程项目的计量，均应按本规则规定或监理人书面指示进行",true,{"key":16,"text":17,"correct":14},"B","除非监理人另有准许，一切计量工作都应在监理人在场情况下，由承包人测量、记录",{"key":19,"text":20,"correct":21},"C","工程量必须由承包人和监理人共同计算",false,{"key":23,"text":24,"correct":14},"D","超过图纸所示的面积或体积，不予计量与支付",{"key":26,"text":27,"correct":14},"E","全部必需的模板、脚手架、装备、机具、螺栓、垫圈和钢制件等其他材料，均不单独计量","ABDE","本题考查的是工程计量规则的说明。工程量应由承包人计算，由监理人审核。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]