[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106206":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106206,781,2,"多选题","以下的计量规则中，正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","已标价工程量清单中的工程量为估算工程量",true,{"key":16,"text":17,"correct":14},"B","承包人未在已标价工程量清单中填入单价的子目，不予计量",{"key":19,"text":20,"correct":14},"C","监理人可通知承包人共同进行联合测量",{"key":22,"text":23,"correct":14},"D","一般情况下承包人对已完成的工程进行计量，向监理人提交有关计量资料",{"key":25,"text":26,"correct":27},"E","监理人应要求承包人派员共同对每个子目的历次计量报表进行汇总，施工单位可以拒绝",false,"ABCD","本题考查的是工程计量的基础知识。为核实最终结算工程量，监理人应要求承包人派员共同对每个子目的历次计量报表进行汇总。承包人未派员参加或未达到监理人要求的，以监理人最终核实的工程量为承包人完成该子目的准确工程量。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]