[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106205":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106205,781,2,"多选题","招标控制价的作用包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","利于引导投标方投标报价",true,{"key":16,"text":17,"correct":18},"B","是建设工程计价的依据",false,{"key":20,"text":21,"correct":14},"C","增强招标过程的透明度",{"key":23,"text":24,"correct":14},"D","可为工程变更新增项目确定单价提供计算依据",{"key":26,"text":27,"correct":14},"E","作为评标的参考依据","ACDE","招标控制价的作用包括：①招标人有效控制项目投资，防止恶性投标带来的投资风险；②增强招标过程的透明度，有利于正常评标；③利于引导投标方投标报价，避免投标方无标底情况下的无序竞争；④招标控制价反映的是社会平均水平，为招标人判断最低投标价是否低于成本提供参考依据。⑤可为工程变更新增项目确定单价提供计算依据；⑥作为评标的参考依据，避免出现较大偏离；⑦投标人根据自己的企业实力、施工方案等报价，不必揣测招标人的标底，提高了市场交易效率；⑧减少了投标人的交易成本，使投标人不必花费人力、财力去套取招标人的标底；⑨招标人把工程投资控制在招标控制价范围内，提高了交易成功的可能性。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]