[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106187":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106187,781,2,"多选题","施工方案的技术经济指标体系中，工程工期包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工机械化程度",false,{"key":16,"text":17,"correct":14},"B","安全生产",{"key":19,"text":20,"correct":21},"C","工期",true,{"key":23,"text":24,"correct":21},"D","施工均衡性",{"key":26,"text":27,"correct":21},"E","竣工率","CDE","施工方案的技术经济指标体系有： ①工程成本包括：单位工程量成本、工程成本降低率（或成本节约额）、工料节约率（或主要材料消耗指标）、劳动生产率（或劳动力消耗）、机械利用率。 ②工程工期包括：工期、施工均衡性、竣工率。 ③工程质量包括：合格品率、优良品率。 ④其他包括：施工机械化程度、安全生产、文明施工等。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]