[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106171":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106171,781,2,"多选题","分项工程质量评定合格应满足的要求包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","所含分部工程应合格",false,{"key":16,"text":17,"correct":14},"B","所含分项工程及实测项目应合格",{"key":19,"text":20,"correct":21},"C","检验记录应完整",true,{"key":23,"text":24,"correct":21},"D","实测项目应合格",{"key":26,"text":27,"correct":21},"E","外观质量应满足要求","CDE","分项工程、分部工程、单位工程质量评定应有符合JTG F80\u002F1—2017附录K规定的资料。A项，单位工程质量评定合格应符合下列规定：①评定资料应完整；②所含分部工程应合格；③外观质量应满足要求。B项，分部工程质量评定合格应符合下列规定：①评定资料应完整；②所含分项工程及实测项目应合格；③外观质量应满足要求。CDE三项，分项工程质量评定合格应符合下列规定：①检验记录应完整；②实测项目应合格；③外观质量应满足要求。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]