[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106161":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106161,781,2,"多选题","公路工程交工验收的条件包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","合同约定的各项工程已全部完成",true,{"key":16,"text":17,"correct":14},"B","施工单位按评定标准已做了自检，且合格",{"key":19,"text":20,"correct":14},"C","监理工程师对工程质量评定合格",{"key":22,"text":23,"correct":14},"D","质量监督机构对工程质量评定合格",{"key":25,"text":26,"correct":27},"E","建设单位对工程质量评定合格",false,"ABCD","本题考查的是质量评定与验收。交工验收的条件：合同约定的各项内容已全部完成； 施工单位按《公路工程质量检验评定标准第一册土建工程》（JTGF80\u002F1—2017）及相关规定对工程质量自检合格；监理工程师对工程质量评定合格；质量监督机构按交通运输部规定的“公路工程质量鉴定办法”对工程质量进行检测（必要时可委托有相应资质的检测机构承担检测任务），并出具检测意见；竣工文件已按交通运输部规定的内容编制完成；施工单位、监理单位已完成本合同段的工作总结。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]