[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106128":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106128,781,2,"多选题","以下属于施工阶段质量监理内容是（）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","审批施工测量放线",true,{"key":16,"text":17,"correct":14},"B","监理机构应审查施工单位报审的原材料和混合料试验资料",{"key":19,"text":20,"correct":21},"C","编制监理计划",false,{"key":23,"text":24,"correct":21},"D","编制监理细则",{"key":26,"text":27,"correct":14},"E","监理工程师应对施工单位报验的隐蔽工程进行检査验收，留存影像资料","ABE","CD属于施工准备阶段质量监理的内容",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]