[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106105":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106105,781,2,"多选题","隧道施工常采用的开挖方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","直线法",false,{"key":16,"text":17,"correct":18},"B","全断面法",true,{"key":20,"text":21,"correct":18},"C","台阶法",{"key":23,"text":24,"correct":18},"D","导坑超前法",{"key":26,"text":27,"correct":14},"E","逐段开挖法","BCD","通常采用的开挖方法大体可分为三种：①全断面法。适用于地质稳定的地层中，在大断面隧道施工中，开挖和支护衬砌能够使用大型机械，能实现机械化快速施工，且开挖一次完成，不存在多次挠动围岩情况；②台阶法。一般指上半断面与下半断面同时并进的开挖方法。在围岩条件或施工机械不适合全断面法施工时可采用这种开挖方法；③导坑超前法。包括侧导坑超前、下导坑超前、上导坑超前等。其中侧导坑超前是在断面较大，围岩支承力不够的情形下，以及限制覆盖层薄地表下沉的地段使用这种开挖方法，由于其开挖、支护施工较为复杂。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]