[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106104":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106104,781,2,"多选题","隧道工程施工组织总设计的内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制的依据和原则",true,{"key":16,"text":17,"correct":18},"B","人员组织机构图",false,{"key":20,"text":21,"correct":14},"C","施工总进度和季（月）计划",{"key":23,"text":24,"correct":14},"D","施工总平面图",{"key":26,"text":27,"correct":14},"E","技术经济指标","ACDE","隧道工程施工组织总设计的内容有：①编制的依据和原则；②建设项目工程概况（项目用途、工期、经费来源、自然条件、环境条件、勘探资料）；③施工计划及主要施工方案（正常施工、特殊施工）；④施工准备工作计划（任务划分、工序安排、劳动力组织、经济安排、临时设施）；⑤施工总进度和季（月）计划；⑥资源需要量计划（材料、水、电、气、设备、人员）；⑦施工总平面图；⑧主要施工技术措施（包括采用新技术、新工艺）；⑨质量、安全、节约的技术措施；⑩技术经济指标。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]