[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106092":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106092,781,2,"多选题","关于隧道开挖后的稳定措施，以下说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","仰拱任意时间施工",false,{"key":16,"text":17,"correct":18},"B","选择稳定掌子面方法有：环形开挖留核心土、缩短进尺及支撑间距及早形成闭合支护",true,{"key":20,"text":21,"correct":18},"C","稳定掌子面的辅助方法有：超前管棚、预注浆固结、插钢板支护等",{"key":23,"text":24,"correct":18},"D","特殊地层中稳定掌子面的特殊方法有：帷幕注浆、井点降水、冻结法等",{"key":26,"text":27,"correct":18},"E","坚持“短进尺、弱爆破、强支护、早闭合”的开挖施工原则","BCDE","本题考查的是隧道开挖施工质量监理。仰拱最好在二次衬砌之前施工，使支护体系尽早形成封闭系统。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]